Glen B. Alleman was kind enough to respond to one of my recent posts, taking exception to my assertion that a simple, calculated estimate at completion (EAC) is probably the most powerful underused tool at the project manager's disposal.
He laid out a scenario where a varied time-phased budget (Budgeted Cost of Work Scheduled, or BCWS) would introduce a sufficient level of error into the calculated EAC so as to significantly reduce its effectiveness.
I must disagree, if, for no other reason, than the time-phased budget isn't part of the calculation.
As I discussed in that earlier post, the classic cost performance index divided into the budget at completion formula can be algebraically simplified to dividing cumulative actuals by the estimated percent complete. With those two data points, remarkably accurate management information can be gleaned and used to avoid project catastrophe.
To support my argument, I would like to ask: What other options are out there? What other methods can rival the simple earned value management (EVM) version?
After suffering through semesters and semesters of accounting, and semesters and semesters of finance, I can say with a fair degree of certainty that there's nothing in the accountant's toolbox that can even come close to the accuracy of the simple EVM method.
As counter-intuitive as this may sound, the person who has been through a 40-hour EVM class is in a far superior position to relay accurate at-completion project costs than is the accountant, who, of course, needed years and years of post-secondary education.
I intend to speak on this at the EVM World 2009 conference being put on by the PMI College of Performance Management this week. If you're in attendance, look me up. Otherwise, leave a comment. I'll see it, I promise.
He laid out a scenario where a varied time-phased budget (Budgeted Cost of Work Scheduled, or BCWS) would introduce a sufficient level of error into the calculated EAC so as to significantly reduce its effectiveness.
I must disagree, if, for no other reason, than the time-phased budget isn't part of the calculation.
As I discussed in that earlier post, the classic cost performance index divided into the budget at completion formula can be algebraically simplified to dividing cumulative actuals by the estimated percent complete. With those two data points, remarkably accurate management information can be gleaned and used to avoid project catastrophe.
To support my argument, I would like to ask: What other options are out there? What other methods can rival the simple earned value management (EVM) version?
After suffering through semesters and semesters of accounting, and semesters and semesters of finance, I can say with a fair degree of certainty that there's nothing in the accountant's toolbox that can even come close to the accuracy of the simple EVM method.
As counter-intuitive as this may sound, the person who has been through a 40-hour EVM class is in a far superior position to relay accurate at-completion project costs than is the accountant, who, of course, needed years and years of post-secondary education.
I intend to speak on this at the EVM World 2009 conference being put on by the PMI College of Performance Management this week. If you're in attendance, look me up. Otherwise, leave a comment. I'll see it, I promise.
If offered benefits are greater or equal than expected benefits, satisfaction is achieved. If available resources are greater or equal than required resources, value can be realized. 
